CONCEPT: Time and Work
-Calculate unit work to breakdown data for 1hr or 1 day.
SOLUTION:
Work of A in one hour=1/10
B+C in 1 hour=1/4
A+B+C=(1/10+1/4) in 1 hour=14/40 products
Given, total number of products they completed working together=14
Hence total time to complete= 14/(14/40)=40 hrs.(C)